The ultimate goal of LOS survey is to have MW connectivity between the two sites to ascertain the Line of Site clearance. The LOS survey is carried out physically checking the terrain between the hop and selecting the sites for acquisition. The survey is highly critical because any failure in LOS can lead to a delay in project and a subsequent loss on account.

LOS survey is carried out in the following steps:

  • Collect Nominals of proposed site and those of the nearest locations to which customer proposes the LOS connectivity & Verification
  • Record latitude, longitude, building data, obstruction data and surrounding terrain data on the LOS Survey template
  • Generate LOS Path Profile for the proposed Link using Pathloss 4.0
  • Generate LOS report for the proposed Link using Pathloss 4.0.Conduct physical survey of the hop to identify any field obstructions and verify the LOS path profile